DRI Project Updates
Here, you'll find the latest updates on the Main Street and Groton Avenue construction projects, as well as other key city-wide developments shaping our community. We’re committed to keeping you informed every step of the way as we build a stronger, more vibrant downtown Cortland.
​
For the most up-to-date information, be sure to follow us on Facebook at @CrownCityRising.
Main Street
Week of June 23
​​
​Final course paving on Main Street begins Monday, June 23 and is expected to take five days, weather permitting. During this time, drivers can expect temporary street closures, alternating lane closures, and limited parking downtown.
​
Final striping is scheduled for the week of June 30, and the big change is coming soon — Main Street officially converts to two-way traffic on Friday, July 11. Digital message boards will be placed on Port Watson/Tompkins Streets and Clinton Ave/Groton Ave to alert drivers of the upcoming shift.
​
Parking Updates
To accommodate next week’s Main Street paving, the City of Cortland is suspending daytime parking regulations in all seven municipal parking lots from June 23–30.
​
Visitors are encouraged to park in these lots while Main Street parking is restricted during the 4–5 day paving process (weather dependent).
Please note: Overnight parking rules will still be enforced.
​​
Please note, all detours and construction activity is subject to weather and other related variables.
Groton Ave
Week of June 23
Crews are conducting restoration work including installing new topsoil and grass seed. Some minor road work is planned in preparation of the finish paving on Groton Ave.
​
Please note, all detours and construction activity is subject to weather and other related variables.
City of Cortland
Week of June 23
​
PROJECT #1​​
​
The City of Cortland’s 2025 paving schedule is underway, and we’re getting ready to roll out smoother streets across several neighborhoods. Crews will begin milling and base paving June 4–9, with final asphalt placement scheduled for June 23–27 on select streets.
​
June 4–9: Milling & Base Paving
• Sands Street
• Bellrose Ave
• Ellwood Ave
• Forrest Ave
• Melvin Ave
• N. Atkins Ave
• Glenn Street
Note: Milling on Clayton Ave may begin this week to allow DPW to replace the concrete curbing.
​
June 23–27: Final Asphalt Placement
• Bellrose Ave
• Ellwood Ave
• Forrest Ave
• Melvin Ave
• N. Atkins Ave
• Glenn Street
​
Please use caution in these areas and watch for crews and signage. Additional streets will be announced once this phase of work is complete.
​
PROJECT #2
​
Pendleton St (Clinton Ave – Elm St) & Elm St (Pendleton St - #56 Elm) – Plan Start May 1 – Est. Duration 7-8 Weeks
​
Most of the work will take place off-road behind the curb. The road will remain open to all through traffic for the majority of the project, though intermittent single-lane closures with flaggers may occur as needed. Short-term (1-2 hour) full closures will be required during gas main road crossings at Pendleton & Garfield and near #56 Elm; DDS will notify the City 1-2 days in advance so the public and emergency services can be informed.
Gas services on the west side of Pendleton St and both sides of Elm Street will be transferred to the new gas main. Residents in the project area should be receiving letters outlining the work to be done. Permanent restoration—including topsoil, seed, asphalt, and sidewalk replacement (where asphalt or sidewalk was disturbed) will take place after all work is complete. ​
​
Please note, all detours and construction activity is subject to weather and other related variables.